Sand Dredge Relocation

Sand Dredge Relocation

Dredge Relocation Project The Dredge Relocation Project, valued at $26M AUD, was a significant part of a mine capacity expansion project which required upgrading equipment and systems on the floating Concentrator to tie-in the new dredge. The dredge project comprised...
Rotary Cooler Replace

Rotary Cooler Replace

Rotary Cooler Replace The Rotary Cooler Replacement Project involved the replacement of the 380 tonne, 60m x 4.8M, cooler.  Track cranes (750t and 250t) were contracted to walk-out the 17m of cooler from within the transfer building. There was only 900mm of clearance...
Tank, Tank Top, Tank Lining, & Launder Replacement

Tank, Tank Top, Tank Lining, & Launder Replacement

Tank, Tank Top, Tank Lining, & Launder Replacement The project required the replacement of the acid tank and cyclone prep tanks, and the tank tops of 5 other corrosive and flammable substance.  Multi hydraulic cranes (250t, 150t, 125t, and 40t) were used for...
Rotary Kiln Refractory Project

Rotary Kiln Refractory Project

Rotary Kiln Refractory Project The project required the demolition and replacement of approx 55% of the 90m x 5m rotary kiln refractory, replacement of shell tubes, and upgrade transimitters.  A ten linear metre section trialled the use of Stud Welding and Shotcrete...
Sizer Screen Replacement Project

Sizer Screen Replacement Project

Sizer Screen Replacement Project The Mogensen Screen replacement required “out-of-the-box” brain-storming to analyse and plan the manoeuvring of the 20 year old 800kg mogensen screens out of the building, and to install the replacement screens safely.  Temporary...
Waste Gas Stack Remove, Repair, & Reinstallation Project

Waste Gas Stack Remove, Repair, & Reinstallation Project

Waste Gas Stack Remove, Repair, & Reinstallation Project The Waste Gas Stack project involved the removal of 4 of vertical 11m x 3m fibreglass stack sections to be sent offsite for fibreglass repair of internal delamination’s, then reinstall on return to site. ...
HP Flare Ignition Replacement Project

HP Flare Ignition Replacement Project

HP Flare Ignition Replacement Project The flare ignition replacement project involved the replacement of the flame front ignition control panel, all ignition cable, gas piping and igniter; and the repair  and or replacement of damaged flare heads. Critical to the...
Miscellaneous Works

Miscellaneous Works

Miscellaneous Works Miscellaneous work activities to inspect and or replace pressure vessel and tank structure, valves, gaskets and instrumentation.. 15. 4E2308 – LNG GAS COOLER – LNG Cooler Over View 14. 4PSV635 – PSV PROD WATER SKIM TNK PIPING...